UAT is the business confirming that the solution supports the way it will actually work. It is not a training course, a demonstration or the first time anyone has tested the system, although on many CRM projects it ends up being all three. When UAT turns into discovery, change requests flood in, dates slip, and acceptance is given under pressure rather than on evidence.
Good UAT is short, scripted and run by the people who will use the system, logged in with their real security roles, against data that looks like their own. The scripts come from the acceptance criteria agreed when the user stories were written, so the business is checking what it asked for.
When to use
- Writing UAT scripts and the UAT plan.
- Setting UAT entry and exit criteria.
- Choosing business testers by role coverage and declared availability, and briefing them.
- Running daily UAT triage and separating defects from change requests.
- Preparing UAT sign-off for the go-live decision.
Not this skill: business-analysis:acceptance-criteria for writing the criteria, testing-quality:system-integration-testing for technical end-to-end proving, change-adoption:role-based-training for training end users, and programme-management:go-no-go for the release decision.
Questions to ask first
- Are acceptance criteria written and agreed for the stories in scope? Without them, scripts become opinions and sign-off becomes a negotiation.
- Which business roles must accept, and which testers have declared availability for the UAT window? Choose testers for role coverage and availability, never on assessments of individuals.
- Has SIT exited, and is the UAT environment deployed from the pipeline with migrated data? Starting early wastes testers' time on known defects.
- Who has authority to sign off each process area? Sign-off from someone without that authority will be reopened after go-live.
- Do testers hold the licences needed to use the UAT environment? Confirm with the Microsoft licensing guide or your partner.
Approach
- Derive scripts from acceptance criteria. Each script follows a business scenario in business language (a day in the life of a role), cites the stories and criteria it proves, and states the expected outcome. Keep scripts at the level of what the user does and sees rather than field-by-field click paths, so testers notice when the process feels wrong.
- Set entry criteria. SIT has exited with no open critical defects; the UAT environment is deployed with managed solutions; security roles, teams and queues are configured as for production; migrated data is loaded; testers have had a short navigation briefing and know how to log defects; process owners have reviewed the scripts. Whether real customer data may sit in UAT is a decision for the organisation's DPO or legal adviser.
- Set exit criteria. All scripts executed; no open critical or high defects unless each has an accepted workaround recorded; medium defects carry a fix plan; each process owner has signed off.
- Use one severity scale, the one agreed in the test strategy. A workable scale is: critical (a core process cannot be completed and there is no workaround), high (a process is seriously impaired or the workaround is costly), medium (wrong but workable), low (cosmetic). Separate change requests from defects: a defect is the system failing an agreed criterion, and anything else is a change request routed to change control.
- Run UAT as a managed event. Hold a short daily stand-up and triage, keep a visible tracker of scripts executed and defects by severity, have consultants on hand to reproduce issues, and plan a fix-and-retest window into the schedule rather than hoping for one.
- Close formally. Record what was tested, by which roles, with what outcome, and which defects are carried into go-live with owners and dates.
Test as real users. Business-unit and team-based access, field-level security and queue membership produce exactly the defects that administrator testing hides. For Field Service, technicians should test on Field Service Mobile with their actual devices; for Contact Center channels, include live agent sessions with real routing.
Outputs
- UAT plan, scripts and tracker within
test-strategy-and-uat-scripts. - UAT entry and exit checklist.
- Defect log with severity and disposition, plus a change request list routed to change control.
- UAT sign-off record per process area, feeding
programme-management:go-no-go.
Scale notes
SMB
A handful of business testers over a short window is normal, with the consultant preparing scripts and running triage. Keep sign-off formal even when the sponsor is also a tester. Do not let UAT double as end-user training; if testers are meeting the system for the first time, run a short orientation before scripts start.
Enterprise
UAT runs per workstream and then end to end across modules, with a UAT manager, test leads and process owners who sign off. Plan tester backfill with line managers well ahead, run a dedicated triage board, expect more than one round, and keep an audit trail of sign-offs. Languages, currencies, time zones and accessibility need their own scripts.
Hand-offs
programme-management:go-no-goreceives the UAT exit report and the list of carried defects.support-operations:cutover-plantakes the accepted build into cutover;support-operations:hypercareinherits carried defects.change-adoption:role-based-trainingreuses UAT scenarios as a basis for training.- Change requests raised in UAT go to
design-authority:change-impact-assessment; access findings go tosecurity-compliance:security-model-review.
Sources
references/sources.md in this skill lists the outside authorities for the questions here, what each is authoritative for, and what you may do with it. Check the current Microsoft Learn documentation before stating how a feature behaves, because Dynamics 365 changes monthly, and cite what you used.
Never
- Let consultants or developers execute UAT scripts on behalf of business testers.
- Run UAT logged in as System Administrator.
- Accept sign-off from someone without authority for that process area.
- Relabel change requests as defects to get them built before go-live.
- Rate or rank individual testers in UAT reports.
Sources for this skill
AI at Work roadmap
- Publisher: Microsoft (Global)
- Link: https://www.microsoft.com/en-gb/microsoft-365/roadmap
- Authoritative for: Planned and rolling-out capabilities for Dynamics 365, Power Platform and Dataverse since the move away from release plans in 2026.
- What you may do: Read and cite. Summarise in your own words; do not reproduce the text.
- Last checked: 2026-10-15
Introduction to the Success by Design framework
- Publisher: Microsoft (Global)
- Link: https://learn.microsoft.com/en-us/dynamics365/guidance/implementation-guide/success-by-design
- Authoritative for: The five Success by Design stages and the review points Microsoft and partners use to address project risk.
- What you may do: Read and cite. Summarise in your own words; do not reproduce the text.
- Last checked: 2026-10-15
Web Content Accessibility Guidelines (WCAG) 2.2
- Publisher: W3C (Global)
- Link: https://www.w3.org/TR/WCAG22/
- Authoritative for: Accessibility success criteria for portals, forms, emails and custom controls.
- What you may do: Reuse terms not yet confirmed. Treat as read and cite only.
- Last checked: 2026-10-15
Credit
This skill was created by Simon Foote and Robert Peledie as part of D365Forge, licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). Credit them when you share or adapt it; see https://github.com/SimonFoote-greensparx/D365Forge/blob/main/NOTICE.md.